Needles Airport Runway Reconstruction
Needles, CA

Client
County of San Bernardino
Contact
Associated Engineers
Mr. Jim Imbiorski
909-980-1982
Construction Cost
$800,000
Completion
2004
RMA Group has provided geotechnical engineering, construction inspection and quality assurance materials testing services for the recently completed pavement reconstruction project at Needles airport. The existing surface of Runway 11/29 and the parallel taxiway were severely damaged from the years of use. Therefore, repair was needed for the 5,000 x 150-foot runway and associated parallel Taxiway “A”. RMA provided a geotechnical investigation and pavement evaluation for the existing runway to assist in determining the most economical means of rehabilitation. RMA Group provided a design of an asphalt concrete pavement structural section, which utilized grindings obtained by processing the existing asphalt concrete section as a base course and minimized the cost of replacing the existing pavements.